MGH begins the Early Contractor Involvement process
The Murchison Green Hydrogen (MGH) Project closed out the pre-Front End Engineering Design (FEED) studies in late 2024.
The Murchison Green Hydrogen (MGH) Project closed out the pre-Front End Engineering Design (FEED) studies in late 2024.
Prior to commencing FEED phase of the Project in 2026, MGH will be completing an Early Contractor Involvement (ECI) process. This process will see the Project engaging with suitable Engineering, Procurement, and Construction (EPC) contractors and selecting contractors to engage in refining the current design to reduce uncertainties around the design and construction methodologies.
The ECI will be a competitive process with at least two contractors working in parallel with the goal being to deliver an optimised design for each of the main Project work packages.
By the end of this process, a single contractor will then be selected to take each work package into the FEED phase of the Project.
To this end, the ECI process has three main objectives:
MGH is seeking input on the current Project concept and construction philosophy to enhance the overall value of the project through minimisation of uncertainties, reduced capital or operational expenditure (CAPEX or OPEX) or enhanced plant availability. The Project will be seeking lessons learned from contractors experienced in similar projects in order to achieve this.
Through the MGH teamβs early engagement with the potential EPC contractors, the Project will be seeking certainty in both the cost and timeline of construction of the Project ahead of commencing the FEED phase.
MGH is seeking to achieve increased confidence in the selection of contractors to complete FEED for the Project and ultimately to undertake the EPC phase. This will be achieved through ongoing interaction with the potential contractors during the ECI process.
The ECI tender process has commenced and is ongoing. The execution of the ECI process is scheduled to take place throughout 2025.
To receive industry updates and express interest in opportunities on the Project, register through our ICN Gateway.
To receive general Project updates, subscribe to our newsletter through the MGH website.
By submitting your email, you accept that your contact information may be collected for the purpose of ongoing communication from and about Murchison Green Hydrogen in accordance with the projectβs internal privacy policy and the Privacy Act 1988 (Cth).